xAI / Southaven / Mississippi / US
This is captive capacity. The operator does not sell GPU-hours, so no price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
Every figure here is one an operator or a filing states, with the sentence it comes from one click away. Nothing is estimated, and an absent figure is rendered as absent rather than left out.
A power or accelerator figure appears above only where an operator or a filing states it. The footprint in the plate's caption is measured from the traced outline rather than published by anyone, which is why it sits there and not in this grid: it is not a capacity figure and it must never be read as the input to one.
Who is stated to occupy this building, and whether any of what is inside it can be bought. Both are claims a source has to make: GPUQuant records a tenant, a partner or a customer only where one is named in a quote.
This is captive capacity. The operator does not sell GPU-hours, so no price on GPUQuant refers to it.
The address on the record, the place it belongs to, and the cloud regions whose named area GPUQuant has tested it against.
GPUQuant records no cloud region relation for this facility. That means neither the geometry test nor a provider statement has put it inside a named area, not that it is unconnected to any cloud.
How this record was built and when it was last checked. A re-run appends a revision rather than overwriting a fact, because the previous value was true when it was recorded and the change is itself the content.
We have entered into an agreed order with the Mississippi Department of Environmental Quality establishing a fixed removal timeline for all 69 of the temporary, mobile turbines that currently power our facility in Southaven, Mississippi.
The 1.2 GW permanent power plant currently under construction will consist of 41 permanent turbines authorized under a Clean Air Act permit, granted to SpaceXAI in March 2026.
SpaceX announced today that it has acquired xAI.
xAI has purchased and is retrofitting a building to house the new data center operations.
The data center, which will be known as MACROHARDRR, is in proximity to xAI’s newly acquired power plant site in Southaven and one of the company’s existing data centers in Tennessee.
The company expects to begin data center operations in Southaven in February 2026.
Recently, xAI announced the purchase of the building formerly used by GXO at 2400 Stateline Road as expansion plans continue in Southaven.
The newest data center will be home to GB 300 processing units for artificial intelligence operations and is expected to bring new job counts in excess of 100 immediately.
According to property records, MZX Tech, an LLC associated with xAI, purchased the property on Dec. 23.
The property at 2400 Stateline Road is a short drive from xAI’s natural gas power plant that the company bought in July 2025.
The location will be on Stateline Road in Southaven, across from the existing power center on Stanton Road.