Amazon Web Services / Hilliard / Ohio / US
Every figure here is one an operator or a filing states, with the sentence it comes from one click away. Nothing is estimated, and an absent figure is rendered as absent rather than left out.
A power or accelerator figure appears above only where an operator or a filing states it. The footprint in the plate's caption is measured from the traced outline rather than published by anyone, which is why it sits there and not in this grid: it is not a capacity figure and it must never be read as the input to one.
Who is stated to occupy this building, and whether any of what is inside it can be bought. Both are claims a source has to make: GPUQuant records a tenant, a partner or a customer only where one is named in a quote.
The address on the record, the place it belongs to, and the cloud regions whose named area GPUQuant has tested it against.
GPUQuant records no cloud region relation for this facility. That means neither the geometry test nor a provider statement has put it inside a named area, not that it is unconnected to any cloud.
How this record was built and when it was last checked. A re-run appends a revision rather than overwriting a fact, because the previous value was true when it was recorded and the change is itself the content.
4120 SCIOTO DARBY CREEK ROAD PARCEL NUMBER: 050-002806 APPLICANT: Amazon Data Services Inc., 410 Terry Avenue N, Seattle, WA 98108
The site is bounded by the CSX railroad to the north and the Conrail railroad to the west.
On August 12, 2021, the Planning and Zoning Commission approved a similar plan for an Amazon data center site located between Cosgray and Leppert Roads.
The site consists of 142.127 acres located at the northwest corner of Scioto Darby Road and I-270. The site is bounded on the north by the CSX railroad and on the west by the Conrail railroad.
The proposal consists of installing 228 fuel cells (outdoor natural gas clean packaged energy servers) in place of the previously approved Building G located in the southern central portion of the site.
This CRA covers the new campuses on Cosgray Road and Scioto Darby Creek Road.
to provide 72.9 megawatts (MW) of power to the AWS Data Center located on Scioto Darby Creek Road