Khazna Data Centers / Abu Dhabi / Abu Dhabi / US
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
Every figure here is one an operator or a filing states, with the sentence it comes from one click away. Nothing is estimated, and an absent figure is rendered as absent rather than left out.
A power or accelerator figure appears above only where an operator or a filing states it. The footprint in the plate's caption is measured from the traced outline rather than published by anyone, which is why it sits there and not in this grid: it is not a capacity figure and it must never be read as the input to one.
Who is stated to occupy this building, and whether any of what is inside it can be bought. Both are claims a source has to make: GPUQuant records a tenant, a partner or a customer only where one is named in a quote.
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
The address on the record, the place it belongs to, and the cloud regions whose named area GPUQuant has tested it against.
GPUQuant records no cloud region relation for this facility. That means neither the geometry test nor a provider statement has put it inside a named area, not that it is unconnected to any cloud.
How this record was built and when it was last checked. A re-run appends a revision rather than overwriting a fact, because the previous value was true when it was recorded and the change is itself the content.
Khazna Data Centers (Khazna) the largest hyperscale wholesale data center provider in the Middle East and North Africa, today solidifies its market dominance with the launch of its flagship data center in Abu Dhabi (AUH6).
G42 today announced major progress on the construction of Stargate UAE, a 1GW large-scale AI infrastructure cluster being developed by Khazna Data Centers, a G42 company, within the 5GW UAE–U.S. AI Campus in Abu Dhabi.
A G42 spokesperson confirmed that construction is now well underway and progressing steadily toward the planned 2026 delivery.
A 1GW Stargate UAE cluster in Abu Dhabi with 200MW expected to go live in 2026
The agreement – which includes our partners G42, Oracle, NVIDIA, Cisco, and SoftBank—was developed in close coordination with the U.S. government, and we greatly appreciate President Trump for his support in making it possible.
Today, in the presence of His Highness Sheikh Mohamed bin Zayed Al Nahyan and U.S. President Donald J. Trump, a new 5GW UAE-US AI Campus, the largest AI infrastructure project outside the U.S., was unveiled.
Building outlines © OpenStreetMap contributors, ODbL. Licence