Novva Data Centers / North Las Vegas / Nevada / US
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
A power or accelerator figure appears above only where an operator or a filing states it.
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
Every change is appended, so an earlier value stays readable beside the one that replaced it.
Construction on the 275,000-square foot, 100MW, $400 Million data center in North Las Vegas began in October 2021, and the facility is expected to open in late 2023.
For context, our Las Vegas data center uses an average monthly water volume equivalent to roughly five typical Las Vegas households.
NOVVA DATA CENTERS EPA Registry Id: 110071941597 6115 NORTH NICCO WAY LAS VEGAS, NV 89115
Facility locations from the U.S. EPA Facility Registry Service. Licence