Loading benchmark data
Menlo Digital / Herndon / Virginia / US
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
A power or accelerator figure appears above only where an operator or a filing states it.
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
None recorded.
Every change is appended, so an earlier value stays readable beside the one that replaced it.
This development site, acquired in June 2023, is a 307,498 square foot two-story data center that has been approved by Fairfax County. Construction commenced Q1 2025.
Here is the current development status for the 13775 McLearen Road site. if you would like to stay updated on progress, please click the button below to be alerted when progress has been made.
The data center will support 48 MW Critical IT.
The two-story, 307,000-square-foot facility will deliver 48 megawatts (MW) of critical IT capacity.