Loading benchmark data
Edged US / Ankeny / Iowa / US
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
A power or accelerator figure appears above only where an operator or a filing states it.
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
Every change is appended, so an earlier value stays readable beside the one that replaced it.
Located on SE 90th Street in the far southeast corner of Ankeny, the 17.5-acre site will house an approximately 105,000 square foot facility with office space and utility infrastructure.
The data center will deliver 13.2 MW of critical capacity, conserve local water resources and minimize energy use.
Edged Des Moines is expected to be fully operational by end of 2026
9100 SE Four Mile Drive, Ankeny, Iowa
Facility locations from the U.S. EPA Facility Registry Service. Licence