Aligned Data Centers / Los Cues / Querétaro / MX
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
No provider names an area that GPUQuant has recorded as containing this building.
A power or accelerator figure appears above only where an operator or a filing states it.
This operator sells space and power, not GPU-hours. No price on GPUQuant refers to it.
None recorded.
Published figures for 2025, from the source named under them.
Who Aligned Data Centers buys from and sells to, each relationship carrying the source that states it.
None recorded.
Buys A data centre provider that Oracle partners with, named as an example by Aligned
Oracle partners selectively with data center providers, such as Aligned Data Centers, that share the commitment to innovation and sustainability.
Oracle Cloud accelerates sustainability commitments by partnering with environmentally conscious data center providers · Aligned Data Centers · read 2026-09-06
Buys Liquid-cooled datacenter capacity at the DFW-04 facility
Lambda will occupy Aligned’s newest Dallas-Fort Worth area facility, DFW-04, which will be designed to be a liquid-cooled data center capable of supporting the highest-density Graphics Processing Units (GPUs).
Aligned and Lambda Partner to Power Next-Generation AI Infrastructure · Aligned Data Centers · read 2026-09-11
Every company Aligned Data Centers deals with, and its own other sites, are on the Aligned Data Centers page.
Every change is appended, so an earlier value stays readable beside the one that replaced it.
QR-03 Data Center
Carretera Estatal 431 – Parque Industrial PyME, Los Cues
Aligned’s Querétaro data centers benefit from new power grid upgrades and expansion, including new transmission lines and two new substations. The project is on track to reach 400 MW of utility capacity.
Ubicado en el Parque Industrial PyMe, en Querétaro, el proyecto resuelve la escasez de energía para centros de datos en la región.
Con la tecnología de enfriamiento de alta eficiencia patentada por Aligned, el Delta Cube, el DC QR03 puede albergar cinco edificios y ofrece la infraestructura robusta necesaria para respaldar implementaciones a gran escala de computación en la nube e inteligencia artificial (IA).
300 MW
Este campus, que comprenderá cinco edificios en una extensión de 275 mil metros cuadrados, tendrá una capacidad total de 300 MW de Tecnologías de la Información al completarse.
El primer edificio ya cuenta con 72 MW listos para operar