Generates or delivers the electricity the racks run on.
vistracorp.com0 sourced relationships.
None recorded.
3 sourced relationships.
Buys 20-year PPA for carbon-free power from the Comanche Peak Nuclear Power Plant
In September 2025, Vistra announced that it had entered into a 20-year PPA (with options to extend for up to an additional 20 years) with AWS, pursuant to which we have agreed to supply to AWS 1,200 MW of carbon-free power from the Comanche Peak Nuclear Power Plant.
vistra-20251231 · Vistra Corp. · read 2026-09-11
Buys 20-year PPAs for carbon-free power and capacity from PJM nuclear plants
In January 2026, we announced that we had entered into 20-year PPAs with Meta Platforms, Inc. (Meta) to supply 2,609 MW of carbon-free power and capacity from our PJM nuclear power plants, including 2,176 MW of operating energy and capacity and 433 of uprate energy and capacity to be constructed.
vistra-20251231 · Vistra Corp. · read 2026-09-11
Buys Nuclear energy from three Vistra plants under 20-year PPAs
Vistra (NYSE: VST) today announced it has entered into 20-year PPAs to provide more than 2,600 megawatts of zero-carbon energy from a combination of three different Vistra nuclear plants to support Meta's operations in the region.
Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid · Vistra · read 2026-09-11
Buys electricity for the Odessa Facility under a power purchase agreement (via Luminant)
In June 2021, we entered into a power purchase agreement with Luminant for the supply of electric power to the Odessa Facility, which was subsequently amended and restated, most recently on August 23, 2023 (as amended, the “Luminant Power Agreement”), pursuant to which we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh, subject to certain increases related to certain tariffs, price increased in October 2025 to 2.8 c/kWh.
cifr-20251231 · Cipher Digital Inc. (formerly Cipher Mining Inc.) · read 2026-09-11
21 U.S. plants under this company's name in EIA Form 860, 12,748 MW operable and 877 MW proposed.
1 recorded, 0 drawn on the map, in one place.